Good afternoon dear, I have a question, I always run the MRP from MD04 entering with a selection rule that excludes sales orders and offers. When entering MD04 with this rule it effectively excludes the sales orders and offers, but when going to MD02 and executing the MRP it brings me the sales order quantities (60 units). Is there any way to exclude the sales orders from the planning? sales orders and offers as well as the selection rule in MD04? I appreciate the guidance you can give me.
Request clarification before answering.
Hi
To exclude sales orders and offers from the MRP planning in MD02 there are a few options, but the most relevant one is configuring the MRP Type and adjusting the settings so that sales orders and offers are not considered during the planning process.
Check MRP Type Settings:
In MD02, the MRP run takes into account specific MRP types that determine which elements are considered for planning. You can modify the settings for the MRP type to exclude sales orders and offers.
Go to Transaction SPRO → Production → Material Requirements Planning → MRP → Define MRP Types.
Here, check the settings for the MRP type used in your materials. Select the MRP type that not consider sale order.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
117 | |
8 | |
8 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.