Hi Friends,

In my project all the plants are defined as" Fund Centers " and with each Fund Center all the cost centers relating to particular plant are assigned in the derivative rule.

Derivative rules defined are as follows:-

GL-Fund Center-Here all the GL accounts are assigned to top node of fund Center.

GL account -Commitment item-Here GL account is assigned to relevant Commitment item.

Budget is assigned for combination of Fund center -commitment item.

My problem is if i dont want to post budget on any line for any fund center then how cope that situation.Because if budget is nt given for any commitment and fund center then while posting on cost center belongs to that particular fund center gives budget exceed message.

Any solution to escape this situation.

Thanks

Deepa

View Entire Topic
deepa_khatri
Active Contributor
0 Kudos

thanks