on 2008 Nov 27 6:11 AM
Hi Gurus
I have a PO with PO qty 100 tons, for which freight will be inconsistant, and there are 4 times GRs are there. For each GR freight will be different. How to add freight while doing MIGO. Can we add Freight in MIGO which will effect to material cost.
Prasad
Request clarification before answering.
Hi Prasad,
U can't give the frieght in MIGO. U can give the planned delivery cost in P.O. Since the GR is done for 4 times, The better option is to go for unplanned delivery cost in MIRO.
Hope this will help you.
With Regards,
Bhaskar.