Formula in Work Centre

Former Member
0 Kudos
69

What is mean by set up formula and processing formula in work centre? How and where they get used?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Set up formula is the formula used to calculate the time to set up a w/c before the actual production starts.

Processsing time is the time required to produce the material (which mainly depends on the qty produced).

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi, Pchetan

you should go through tcodes op7b(to create new parameter) and op21( to create new formula)

Formulas are used for the following pupose

Calculation of execution time

Calculation of capacity requirements

Calculation of costs of a work center's activity type.