For ROH system not creating planned order

Former Member
0 Kudos

Hi PP gurus,

Can anybody tell me that system is not generating planned order for raw material but generating it for its Fert of which it is a bom component. For fert it is giving exception message 62.I checked material master MRP type-M0 FOR FERT MATERIAL

MRP type-PD FOR RAW MATERIAL

pLANNING TYPE FENCE IS ALSO MAINTAINED AS 14 days for raw material

Pl.reply ,it is urgent

Thanks in advance

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

issue is solved or not?

Former Member
0 Kudos

Hi,

Please specify your MRP control parameters.

For Create purchase req- which value is selected(1/2/3).

Exception message 62: Scheduling: master data inconsistent will not have any link for the creation of component Planned order.

Regards,

Krishna Mohan

Edited by: Krishna Mohan N on Feb 8, 2008 11:27 AM

Former Member
0 Kudos

crete PR 2 IN CONTROL PARAMETER,pLANNING MODE 2

Former Member
0 Kudos

Hi,

Is there any specific reason why you want to create planned order for component instead of Purchase requisition?

Check whether system creating Planned order for RM if you specify control PR as"3".

Planning Time fence will not have any influence with MRP type PD.

Regards,

Krishna Mohan

Former Member
0 Kudos

no it is not creting either plannred order or PR.

Former Member
0 Kudos

Hi,

Please Check with routing validity interms Usage, staus,losize, valid from & to priod with requirements dates of planned order

regards

Pardeep.

Former Member
0 Kudos

i CHECKED FOLLOWINGS:

• Check plant specific data in mrp-1 NOT BLOCKED

• Procurement type-F

• Control parameter in md02

• Validity start date of BOM.

2. the number range assigned for purchase requisitions.

3. Check in customising whether default values has been assigned for purchase requisition creation.

MRP-4 MRP dependent reqmt as blank requ

Check active status in OS23

sTILL NOT GETTING

Former Member
0 Kudos

Hi,

In MD04 for that component, is dependent requirement being displayed? What is stock?

Regards,

Krishna Mohan

Former Member
0 Kudos

HI,

sTOCK IS NIL

Former Member
0 Kudos

dEPENDENT REQUIREMENT SHOWING NEGATIVE QTY ,BUT NO PLANNED ORDER

Former Member
0 Kudos

hi,

with which transaction code r u running the MRP??

as per my knowledge u must be doing it with the MD02 with finished product at the header level.

just try this, run the MRP for the Raw material since you are having the dependant requirement with the -ve value, it will create the palnned order.

i am not remebering what is issue?? there is something theorotical,

u just try this

i wil let u knwo furhter once u get the planned order.

in MPS, i am doubtful that it will go for multilevel, thats why its creating only dependant requirement.

you try to run the MRP thr MD01 then u ill get the order.

Let me know ASAP, i will help u out.

REgards

Pravin Mukkawar

Former Member
0 Kudos

Hi,

Please letus inform hoe u run the MRP, from MD41 or MD42.

Please try with MD41 - single item mutilevel.

Regards

pradeep

Former Member
0 Kudos

if procurement type is f why do u need planned order. change procurement type to X and rerun mrp md02

give planneng mode as 3. create purreq as 1