FM to change status of N/W Activity element ?

Former Member
0 Kudos

Hi All,

In CJ20N we have the following hierarchy:-

Proj -> WBS -> Network -> Network activity -> Network activity element

My requirement is that if status of N/w activity is confirmed, then n/w activity element should also be confirmed.

How to change the status of n/w activity element ? Which FM to use ?

Regards,

Ashish

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello

BAPI_BUS2002_SET_STATUS

But you need call transactions in follow sequence:

1. BAPI_PS_INITIALIZATION.

2. BAPI_BUS2002_SET_STATUS.

3. BAPI_PS_PRECOMMIT.

4. BAPI_TRANSACTION_COMMIT.

Answers (1)

Answers (1)

sreeramkumar_madisetty
Active Contributor
0 Kudos
Former Member
0 Kudos

Hi Sreeram,

Thanks for the link.

But, I could not find any BAPI for confirming n/w activity elements.

BAPI_NETWORK_CONF_ADD allows only for n/w activity