cancel
Showing results for 
Search instead for 
Did you mean: 

flow and customizing process of st.grp 11

Former Member
0 Kudos

Hi Guru,

As per my client requrimet they want to implement st grp 11,but i dont what are setting done for that.

Pl let me know for customization purpose how can do the planning using this scenario give detail flow of this st grp along with

business case. what are customization setting for st grp 11 what type result show in system ?

With Regards,

Ravindra.

Accepted Solutions (0)

Answers (6)

Answers (6)

Former Member
0 Kudos

Answered, Plz closed this thread.

with regards,

ravi

Former Member
0 Kudos

Answered, Thanks Team close block.

Regards,

Ravindra.

former_member184574
Active Contributor
0 Kudos

No need for any customization........... just make settings in the material master change the strategy group to 11 in the MRP3 view and other settings if any and proceed.

Former Member
0 Kudos

Dear Ravindra

Please take the following reference ,it will give you information with example

http://help.sap.com/saphelp_46c/helpdata/en/38/1a37e58ccd11d1918c0000e8a5f6e6/content.htm

Regards ,

Vishwas.K

Former Member
0 Kudos

Hi vishwas,

suppose my PIR:1000, Pl order: 1000kg in st grp 11 what happen after production order confirmation basically stock mmbe they are showing any stock? st grp 11 is not consider warhouse stock right, could pl give me any scenario for this i will check.

With regards,

Ravindra.

Former Member
0 Kudos

Hi

Plz follow the below Link

http://help.sap.com/search/highlightContent.jsp

Regards

BRSR

sundaresan_velayudam
Active Contributor
0 Kudos

Master data setting:

in MRP 3 view maintain Strategy 11 and Mixed MRP as gross requirement.

Process Sequence:

Create a PIR in MD61( system will take reqmt type BSF- for strategy 11)

and do the normal production process,

PIR will be reduced, when you do the GR for the production order.

business case: in cement Industry / steel Industry - The production will be continuous eventhough If you have enough stock, the production department won't bother about the inventory In ware house, strategy 11 - won't consider warehouse stock during MRP run