flexible planning

Former Member
0 Kudos

I have created an info structure with key figures of sales , production, target stock level, days supply.

Now when I manuaally put the sales plan of 3months and i have defined target stock level. How can I get the production plan as I am not able to understand Macro creation and execution to get the prod. plan

Amit

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Write the macro as below

Sales - stcok level = Production

Goto planning type you have created and follow the menu path

Mirco --> cretae

give the name and discription

in micro - screen

S = checked

operand = Sales

Op = -

Operand = Stock level

Result = Production

Save the micro

and come back and save. Again goto Planning type

Menu path

goto --> planing type info

default micro = what you have created above

save.

Now go for planning...it will work

Former Member
0 Kudos

Hi Rajesha

I have created macro as suggested by u in planning type.

When I am entering sales plan and target stock level in MC93,create plan consistent planning and executing the macro, Still I amnot able to get the production plan.

Is anything missing

Pl guide me

Amit

Former Member
0 Kudos

Check whether you have that micro in the transaction? just check and come back. I think you have not created the macro properly.

In the planning type itself you check first...with test data..if that works..it will work here also.

Former Member
0 Kudos

hi rajesha

U r absolutely right.But I am facing one problem.

example:

sales 200 300

target stock 10 20

production 210 320

in the second column of production I got 320 but i think it should be 310 because I have got 10 target stock from first col

and i need another 10 to make 20 as target stock in 2nd col. so my production should be 310 in 2nd col.

My macro is sales - target stock =production.

so what changes I need to make in macro

Amit

Edited by: AMIT AGGARWAL on Jan 22, 2008 4:46 AM

Edited by: AMIT AGGARWAL on Jan 22, 2008 5:08 AM

Former Member
0 Kudos

pl give as a link for screen shot of planning type, micro

Former Member
0 Kudos

hi rajesha

I am not able to provide u the link.

my macro:

sales + target stock level = result is production

Amit

Former Member
0 Kudos

in that case the calculation is correct

sales 200 300

target stock 10 20

production = sales + target stock level = 210(20010) 320(30020)?

what uis the issue? it is perfectly calcuation!!!!!!!!!!!!!!!!!!!!

Former Member
0 Kudos

hi rajesha

It is ok, but u can see, I have to carry forward the target stock 0f 10 pc from first col to next col. So,my production should be 310 to keep my target stock of 20 pc in 2nd col (10 from first col left + 10 from 2nd col= 20 as defined in target stock for 2nd col)

Amit

Former Member
0 Kudos

Dear,

Please do as below

Target stock= production - sales.

and create macro and do as i told before...remove the macro created before

Former Member
0 Kudos

hi

The Macro is also not working in mc93(create consistent planning) but it is working in Planning type. How to solve this

and in planning type same problem is happening of calculation which i told u earlier

Amit

Edited by: AMIT AGGARWAL on Jan 24, 2008 7:23 AM

Former Member
0 Kudos

why are you going to MCP3?

Former Member
0 Kudos

hi Rajesha

Sorry its MC93

Amit

Former Member
0 Kudos

hi Rajesha

I have key figures of production , sales. Now I am trying to create macro for disaggregating production.But i am not getting the production key figure at member level. it is only at owner level.

how to get production at member level

Amit

Former Member
0 Kudos

It should be for all levels...please check your settings one again because infostructure created for all the product and levels..

Former Member
0 Kudos

hi Rajesha

what settings i have to check so that key figures are for all levels.

where we have to maintain historical values for forecasting.

thnx in advance

Amit

Former Member
0 Kudos

Hi

Creation of macro is a bit difficult task.

Try to see the std macros like

SOPKAP

SOPKAPAM

SOPDIS

in Tcode MC80

by going through that you may be able to explore.

Regards

YMREDDY

Former Member
0 Kudos

hi

I have tried to create the macro as per standard and I have executed that macro but is inot working

Amit