0 Kudos

Please advise how a flexi work schedule can be created and how absence can be recorded under these circumstance ? i mean +ve / -ve time recording.

Thanks

s

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

to create flexi work schedule DWS

Daily Work Schedule

View: V_T550A

Planned working hours 8,00

Planned working time -

Planned working time 08:00 - 18:00

Normal working time 08:00 - 17:00

Core time 1 09:00 - 11:30

Core time 2 14:00 - 16:00

Work break schedule FLEX

next PWS

Period Work Schedule

View: V_T551A

Grpg PWS Week DWS Period WS text DWS DWS DWS DWS DWS DWS

07 FLEX Flextime001 FLEX FLEX FLEX FLEX FLEX FREE FREE

Former Member
0 Kudos

It says delimit area of validity and what is the DWS claas and purpose? please explain.

Thanks

Former Member
0 Kudos

Hi Srini

You answered my query to an extent..my other part of question is still not addressed..can you help..how time is evaluated when we have public holiday and when only planned working time istaken in consideration..

Thanks

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Susheel,

We eneter the flexible working hours for our DWS this is done in IMG under Define Daily Work Schedule, table is V_T550A

Absences can be recorded as per your requirement with measurement unit hours for that you have to create absence type and absence quotas with time unit hours. However this can be done in other ways as well.

Warm Regards,

'

Kapil Kaushal

Former Member
0 Kudos

Hi there,

I think the flexi work shcedule can be created by using SHIFT PLANNING, and dynamic daily work schedule configuration .

THANKS