Can we change the valuation class in the material master once it is assigned.

thanks in adv

sree

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member712491
Active Participant
0 Kudos

Hi Srilatha,

This is not possible if one or more of the following already exist for the material:

$ Valuated stocks in the current period or in the previous period

$ Open purchase orders or delivery schedule lines

$ Production orders for which a goods movement has already taken place

However if you want to change it anyway please read on.

@ <b>If valuated stocks already exist, you can change the valuation class

only as follows:</b>

a) Post the stocks of the material to an interim account.

b) Change the valuation class in the material master record.

c) Post the stocks of the material back to their original account.

@ <b>If open purchase orders already exist</b>, you can only change the

valuation class if you first flag the corresponding purchase order

items for deletion.

@ <b>If production orders exist for which a goods movement</b> has already

taken place, you can only change the valuation class if you first set

the status of the production orders to Deleted.

Kindly let me know if it helps.

Former Member
0 Kudos

Yes.

it would be advisable to do this at month end, but it can be done anytime.

You will have issues regarding reversals of documents, and posting credits etc.

You could just create a new material with the new valuation class.