the planned order for the SFG has finish dates of 10/14/2008. however, its parent material, the FG, ends on 10/02/2008, 12 days before the SFG's finish. isnt the system supposed to schedule the SFG first, before the FG?
Hi,
Normally system will schedule like this only.
If you want to schedule considering the dep reqmts also, then set the Adjust dates indicator in OPU5 - Adjust Scheduling tab - to Adjust basic dates.dep reqmts to order start .
pls try and comeback
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
>
> Hi,
>
> Normally system will schedule like this only.
>
> If you want to schedule considering the dep reqmts also, then set the Adjust dates indicator in OPU5 - Adjust Scheduling tab - to Adjust basic dates.dep reqmts to order start .
>
> pls try and comeback
what is the difference between "Adjust basic dates.dep reqmts to order start" & "Adjust basic dates.dep reqmts to operation dates"?
Hi Raf
OPU5 - Adjust Scheduling tab - to Adjust basic dates.dep reqmts to order start means material should available at order start time.
And to Adjust basic dates.dep reqmts to operation start means material should available at operation start time as per assignment of component to the operation.
Regards,
R.brahmankar
Hello Raf,
This is because you not have assigned Reduction strategy
either to the operation or in the order type dependent parameters.
If the lot size is higher your Production dates may go outside
the basic dates.
In such case the system tries to reduce the lead time based on the setting defined in the OPU3 and OPU5.
And
You can avoid this by updating material master from routing timing and I have explained you about it before.
As you knows inhouse production time in material master is lot size independent and time of the routing are lot size dependent..
Reward if useful.
Regards,
R.Brahmankar.
Hi Raf ,
What is your scheduling Type? and Strategy for FG and SFG?
Use tcode OPU5, select your plant.
Goto Adjust scheduling field, select Adjust Basic dates, dependent requirement to operation start date.Try with these four option.
Regards,
R.Brahmankar
Edited by: R Brahmankar on Jul 18, 2008 10:21 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
>
> Hi Raf ,
>
> What is your scheduling Type? and Strategy for FG and SFG?
> Use tcode OPU5, select your plant.
> Goto Adjust scheduling field, select Adjust Basic dates, dependent requirement to operation start date.Try with these four option.
>
> Regards,
> R.Brahmankar
>
> Edited by: R Brahmankar on Jul 18, 2008 10:21 AM
i am using detailed scheduling. My FG strategy is 20, SFG is 10. In OPU5 i have already maintained this setting? what is the purpose of this?
Hi Raf,
Scheduling :-Basic dates will be determined for planned orders or Lead time scheduling and capacity planning ?
Convert the plan order into the production oredr and then check the date again?
Or
Remove the strategy of SFG and create new plaaned order with Lead time scheduling and capacity planning and then check the date again.
Pls try this and come back.
Regards,
R.brahmankar
User | Count |
---|---|
92 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.