Hi SAP experts,

Is there a possibility to perform copy solution profile from Test system to Production system (that is not yet go-live but data migration has happened).

We know SAP allows solution profile copy from test system to another test system, and also from production system to any test system - but is there any way to copy the solution profile from test to production system.

Refer to attached screenshot where system appears to allow solution profile copy from Test to Production - the option seems to be enabled. But we want to confirm with SAP community before proceeding whether this will work or not.

Thanks.

View Entire Topic
leonardo_felini
Advisor
Advisor

Hello Syed,

Considering the way that the system is designed, a copy solution profile from a test tenant to a productive tenant is not supported. The idea is that a pre-production (test) tenant is requested, and from there a productive tenant is created. After this first setup, any changes that are going to be performed in the productive tenant should be made through a local change project (created and merged without testing in the productive tenant) or through a remote change project (created in productive, moved to a test tenant and merged back afterwards).

This is briefly documented in KBA 2325556 - Schedule of Solution Profile Copy is Not Allowed:

https://launchpad.support.sap.com/#/notes/2325556

Kind regards,

Leonardo

Support Consultant | SAP Product Support

Community:

SAP Business ByDesign: https://www.sap.com/community/topics/business-bydesign.html

SAP Cloud for Customer: https://www.sap.com/community/topics/cloud-for-customer.html