F110 proposal has been relesed

Former Member
0 Kudos

Dear All,

I am working with f110 as and when we run the proposal after completing of parameters run proposal the system immediately displaying message proposal has been relesed 09.09.2009 and stucked there no further action.

Can any one help me why this is happaning?.

no. 1. The vendor has open items.

b.s.rao

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member194797
Active Contributor
0 Kudos

already discussed several days ago: []

sridevi_p
Active Contributor
0 Kudos

Hi,

Please check the below options -

1. You would have selected scheduling option during proposal and job is released to be processed. Try clicking 'Start immediately' and check.

2. Check if the server is overloaded and if so, check if the proposal could be processed after sometime.

Regards,

Sridevi

Former Member
0 Kudos

Dear Sridevi Garu,

At Scheduling screen we select "Start Immediately" button then only it will go to next screen. I am getting the message and struct

B.S.rao

Former Member
0 Kudos

hi

check is there any user exit available and activated in your system

Former Member
0 Kudos

Thank you very much for your reply there is no user exits

regards

Former Member
0 Kudos

This message was moderated.