on 2011 Apr 28 11:12 AM
Hi,
We are trying to customize our system in order to exclude the planned costs of the project of the budget availability control.
Example: If once I have budgeted and released the project I add a component to the project I do not want to any error message to appear. Error should only appear once I generated the Purchase Requisition for an amount superior to the WBSE budget.
We have been trying with the customizing point "Define Tolerance Limit", trying with different combination of the Activities Groups but we haven't succeed.
Has anybody tried this before? Could anybody give me a hint?
Thanks a lot
Activity Group 02 represents the orders of the project(Networks), So except 02 and ++ define tolerance limit for all other activity groups and check.
SAP note 628978 explains the transaction groups in detail.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The moment you save the project (after making changes to your project, say, adding new component), system will check against the budget (since AVAC is already active).
We are trying to customize our system in order to exclude the planned costs of the project of the budget availability control.
We have been trying with the customizing point "Define Tolerance Limit", trying with different combination of the Activities Groups but we haven't succeed.
This is not possible.
As an alternative, what you can do it, before adding the new component to the project activity, you need to update your budget (suppliment) with the expected cost of the componet you are adding. This way, you can avoid this error.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Amaresh Makal,
I have not explained well our requirements, or maybe I did not understand your alternative.
We do not want to update the budget, we would like to let users to increase planned costs at any time. What we do not want is "Actual+Commitment" to be higher than the budget.
Actual + Commitment <= Budget --> OK
Planned Cost > Budget --> OK
Thanks all for your answers.
I would like to mention some points about this scenario....
Yes this kind of process is followed when the budget for the WBS is fixed during the bidding phase itself.So that the budget is first allocated to the WBS element and the detail planning by the project engineers under the WBS element happens in the due course of time.
Now I have a doubt in your scenario, when you say actual and commitments are generated.Do they plan the cost first and then convert it into commitments and further actual postings? or Do they generate commitments manually irrespective of whther the material has been planned under the WBS elemnt.If that is your case you may face certain issues like
1) Always you information system report will not give a proper analysis, you should often refer to the budget report for your baseline cost.
2)During period end closing,as the project engineers are permitted to plan at any point of the project, there wont be fixed total plan cost as RA refer only to costs and not to budget.As a result there will be lot of shuffling happening in your Project result reports.
Hi,
By my knowledge its not possible as per your requirement.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Maintian the following settings for Tolerance limit and check,
Transaction Group - ++
Availability Control Action - 3
Usage - 101%
Also check tha budget profile that you have assigned to the Project profile.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.