I got the following Exception message for a planned order in MD04,

20: Cancel process

After getting help for this, system is giving the dignosis that,

"There is no requirements for this receipt. It should be reversed to avoid unnecessary warehouse stock."

What this means?

Regards,

Deven

Accepted Solutions (1)

Accepted Solutions (1)

former_member184627
Active Contributor
0 Kudos

Hi Deven,

Please check the dates in the planned order. This could be before that of the date of requirement.

i.e. If there is no requirement before the date of the planned order then system will propose to cancel the proces...since as per system there is no requirement & hence no need for a planned order.

To check pass a requirement /PIR before that date & then this error will not be displayed.

Regards,

Senthilkumar

Former Member
0 Kudos

Senthilkumar,

I agree that system needs requirement before planned order.

But what if I create planned order without any requirement?

Deven

Former Member
0 Kudos

Hi Devan,

If the planned order is firmed one:-

If any requirement comes in future system has to create planned order. But system consider this old planned order and give rescheduling proposal message if the planned order within rescheduling horizon.

If the planned order is not firmed one:

When MRP run, system delete this planned order, and create new planned order according to Independent req in respective date.

Regards,

Dharma

Answers (1)

Answers (1)

Former Member
0 Kudos

Got satisfied answers...