Even material reach to reorder point system did not generate the PR

Former Member
0 Kudos

Hi Gurus,

This burning issue

minium reorder point 15, maximum stock level 30,available stock 5 procurement type F so it should generate PR

MRP type VB

lot size HB

as per the above said business process system has to generate the PR but in my case system did not generate any PR?

thanks in advance

sapmm

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Did you run MRP in MD01 or MD02. Or is there any open PO. Check the status in MD04 after running MRP

Regards

Antony

Former Member
0 Kudos

Hi Antony,

I have tested in MD04 there is no open po's only it is showing available qty 5

We are running the MRP through background process MDBT then maintain schedule in SM36

pls clarify

sapmm

Former Member
0 Kudos

Once run manually for that material in MD02, If PR is created, then there is a problem in scheduling of MRP. Please check and let me know

Former Member
0 Kudos

Dear Sapmm,

This may be due to lack of Planning file entries. if system could not find planning file entry the it does'nt plan

if not there then create it manually & check the result

T-codes , MD20, MD21

Regards

Madhu

Answers (0)