Hi Gurus,

while calculating variances for production order i am getting the following error

"Cannot calculate scrap variances" ( Error message)

" no standard value estimate for material" (Warning message"

A standard cost estimate exists for the material at the date mentioned in the error in released status.

Please give solution for the error.

Thanks in advance n Regards

Arul.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member188826
Active Contributor
0 Kudos

Is there an <b>itemization</b>, generated for the cost estimate used to calculate the target costs?

Does the material components listed in the BOM of the cost estimate used to calculate the target costs, <b>assigned to the operations</b> in which they are used. Otherwise it is not possible to correctly report the variances and scrap when operations are confirmed.

Does the order for which the variances are calculated have a valid <b>variance key.</b> ?

Does the order have the status DLV (delivered) or TECO (technically completed). If the status was withdrawn, any variances and <b>scrap variances are canceled</b>.