Error when creating document flow for delivery

Former Member
0 Kudos

Hi,

I would like to post the GR for Inbound delivery. I receive an error the TO is not confirmed. I have tried to confirm the tranfer order and I receive the "error when creating document flow for delivery . In order to avoid inconsistencies the goods movement posting was cancelled." It seems like the document already exist.

How can I do to confirm the TO and post the GR.

Thanks

Dede

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

In Inbound delivery after GR only a TO is created and confirmed.

So please check the PO history and see a GR is there or not .

Once a GR is found create a TO and do the confirmation

Former Member
0 Kudos

there is no Po history.

I have created a PO for subcontracting with Me21N. and I did GI with ME2o.

now I want to post the GR.

I don't understand why this error