Error to change the scheduling agreement

Former Member
0 Kudos

after creating the scheduling agreement, i tried to modify the scheduling agreement that does not have a Delivery Schedule using ME32L. and I got an Error message FGV004 - "SYST:date 00.00.0000 is not expected". however, if i updated the delivery schedule, i didn't get the error message when I modified the scheduling agreement. any suggestion?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi AP,

the question is the smiliar, but I'm looking for notes in MM area, not FM area.

Elaine

Former Member
0 Kudos

hi

check this sap Note 1232721 - Error FGV004 when modifying an scheduling agreement