I am getting an error "please specify a valid MRP procedure" when I tried to to enter MRP type VV.

In Error details I am geting "You have specified an unsuitable MRP type. This is because quantity updating is not defined for the current material type in the specified plant."

Please help.

View Entire Topic
pmbwebsites
Discoverer
0 Kudos

1)SOLUTION- OMDU

SPRO --> MM --> Consumption Based Planning --> Planning --> Activate Material Requirements Planning

*)SELECT -ACTIVATE MATERIAL REQUIREMENTS PLANNING

5.png

*)SELECT -PLANT -PUNE AND MUMBAI - TICK-ACTIVATE REQUIREMENT PLANNING

6.png

SAVE

https://www.learntosap.com/mmerrorpage13.html