Erro MD15 Requisições canceladas.

rodrigorieperr
Explorer
0 Kudos

Bom dia , a fábrica onde eu trabalho utiliza, a transação MD15 para gerar RC , porem o usuário alega que as RC geradas estão sumindo de um dia para o outro.

Alguém já passou por isso ?

Accepted Solutions (1)

Accepted Solutions (1)

former_member197616
Active Contributor
0 Kudos

Pl ask ur basis if they have mrp run batch jobs

Do they have approval process in force?

If u have a materiak no known check who is mrp controller and try check the table eban.

rodrigorieperr
Explorer
0 Kudos
I did the test with the user and verified that the fixation code was not being marked.
 

Thanks a lot for the help 🙂

Answers (1)

Answers (1)

former_member197616
Active Contributor
0 Kudos

Pl check a re run of mrp is being done?

Are u converting them into prs or production orders?

rodrigorieperr
Explorer
0 Kudos

in PRS, I suspect they are generating the MRP twice a day and that's why they are canceling the RC, but I can't identify if that's right.