Hi Experts,

We have E-rec and HR systems on two landscapes. i am trying to do the data transfer from HR system to Erec system using PFAL. In hr system idoc shows a success message, where as in erec system idoc status is 64, and NA is not getting created. CP and bp are getting created in erec system,

The problem is with NA. Please advice.

Regards,

Varun

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Varun,

I assume that the implementation HR_INB_PROCESS_IDOC for BadI HRALE00SPLIT_INBOUND is active. This causes

the error described above.

Could you please inactive the BadI implementation (go to transaction SE19, select 'Classic BadI Implementation' and type

'HR_INB_PROCESS_IDOC' and press 'change'. On the next screen select via menu implementation->deactivate).

This should help to avoid the error caused by E-Recruiting. If the original error still persists or my assumption was wrong, please tell us so we can help you.

Regards,

Bentow.

Former Member
0 Kudos

Hi Bentow,

Appreciate your response. We have deactivated the same and checked but still the problem persists.

Regards,

Varun