After compensation planning is saved or submitted for an employee, the budget is locked and cannot be reset to planning mode. Do you know a way around this error? I have a business requirement to modify the budget after compensation planning is started.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

To my knowledge, budget cannot be reset to planning once some of it has been spent. If not, you can use "reset to planning" functionality.

Donnie

Former Member
0 Kudos

Yes, correct...that is how it works standard. I'm trying to figure out a way to override the hard stop error.

Former Member
0 Kudos

One way out is to create a new budget and process it or you can use budget reassignment functionality but that would only move the amounts and not the budget units from one org. unit to other.

Donnie

vtgopalraj
Active Participant
0 Kudos

You have an option to delete the budget related table enteries in HRPADPM