Hi Gurus ,

We plan to upgrade ECC 6 from R/3 4.7, I have one doubt in this,

can we upgrade R/3 4.7 PRD system to ECC 6 DEV system.

If it is possible, kindly give the procedures involved in it.

Regards

Selvan.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sunny ,

Thanks for your reply , I read the guide , Kindly as for your concern shall i correct .

STEP 1. EXPORT the Data using Installation Master in the Live Production System as SID PRD

STEP 2. IMPORT the Data using Installation Master into the test system as Development system DEV .

The above steps are correct for changing our Productio System to Development System ?

Regards

PalaniSelvan

sunny_pahuja2
Active Contributor
0 Kudos

Hi,

First thing I want to make aware about is you will not be able to change database schema...after copy database schema of DEV environment will also be of production...

Then Steps:

1) you have to export Java if it is double stack system..

2) database export and other things that you have to follow from SAP guide

also, if you want that after system copy same configuration your DEV system have (configuration means RFC's, logical systems etc..) then before system copy you have to take backup of these configurations...

after that you have to import Java, restore database and perform other steps..

For details I will suggest you to follow SAP System copy guide...

Thanks

Sunny

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Sunny ,

Can you tell me the steps involved , Because i have to convert our R/3 Production system all data including configuration to as new R/3 Development Server for using Develeopment function .

Kindly tell me the steps involved.

Regards

PalaniSelvan

sunny_pahuja2
Active Contributor
0 Kudos

Hi,

I will say follow SAP system copy guide....I am giving some points that you must do before system copy so that after system copy you have production data but configuration of development system...

1) Take user master export of source system

2) Take a record or screenshot of (TMS Configuration, printer settings, logon group, operation modes, RFC destinations, WE20 partner profiles, We21 ports in Idocs processing, client destinations, logical system names, email configuration, SAP housekeeping jobs and customer specific jobs, ssl config..

3) for RFC backup, expoprt tables RFCDES, RFCTTRIB, RFCCHECK, RFCDESSECU, RFCDOC, RFCGO, RFCSYSACL, RFCTA, RFCTRUST, RFCTYPE

Please also go though sap note970518, 400241

Thanks

Sunny

sunny_pahuja2
Active Contributor
0 Kudos

what i can understand from you is that..you want to upgrade your Development envirónment after refreshing it from production environment ..

yes it is possible..first do the system refresh of your development enviroment from production by system copy method.. Please download system copy guide from below link according to your release:

https://websmp101.sap-ag.de/~form/sapnet?_SHORTKEY=01100035870000670917&;

Then follow the upgrade procedure from SAP 4.7 to ECC 6.0. please find below the link for upgrade:

https://websmp101.sap-ag.de/~form/sapnet?_SHORTKEY=01100035870000670917&;

If you have any other question, please let me know..

Thanks

Sunny