cancel
Showing results for 
Search instead for 
Did you mean: 

DMR

Former Member
0 Kudos
72

in dynamic modification, in "validity of quality level" tab there Reset period (days).

what is that?

Accepted Solutions (1)

Accepted Solutions (1)

former_member204463
Active Contributor
0 Kudos

As you know you`ll be defining inspection stages in DMR, if you want to reset or revert the quality level to initial stage, than you need to mention the reset period after this action to be executed.When an inspection lot is created, the system checks if the reset date for the quality level has been reached or exceeded at each sample calculation. In such a case, it resets the qualiy level to the initial stage of the dynamic modification rule and uses this initial stage for the current inspection lot.

Former Member
0 Kudos

what i understood is -

suppose i created the DMR on 01.01.07. and my reset period is 15 days.

then if i am creating a lot on 15 or after 15.01.07, whatever may be the present quality level, it will reset to initial level and from here again new cycle will start.

is it so?

if so,

thanks a lot.

if not,please clearify.

former_member204463
Active Contributor
0 Kudos

What you`ve understood is absolutely right.

Reward if completly cleared and close the thread.

Answers (0)