DMR - Change Current Inspection Stage

Sevin
Participant
0 Kudos
551

Hi,

I have set up Dynamic Modification at my client and it is working as expected but there are situations where the users want to manually change the inspection stage in the inspection lot. Is there a way to do that? I know I can change the next inspection stage manually in the quality level prior to the PO receipt but cancelling and reprocessing the receipt is not feasible and the warehouse, which processes the receipt, isn't involved in the QA process.

Is there a FM I can use ?

Thanks,

Alas84

View Entire Topic
former_member207800
Active Contributor
0 Kudos

Using transaction QAC3 (reset sample calculation) you can make the status 'CRTD' of inspection lot.

Then assign the inspection plan again at transaction QA02.

Now quality level will be changed.

Regards

Luke

Sevin
Participant
0 Kudos

Thanks Luke- that solved the issue.