distribution in controlling

Former Member
0 Kudos
83

dear all

issue

distribution

common exp are posted in cost centres from 2101000000 to 2101000329

cost elements from 3100000001 to 33999999999 (on the basis of salaries)

cost elements from 3400000000 to 3900000000 (on the basis of turnover(s&d exp)

receiving cost centers two 1. 2101010101 50%

2. 2101020103 50%

Accepted Solutions (0)

Answers (1)

Answers (1)

Adimallaiah
Contributor
0 Kudos

Hi,

You have not highlighted what is the issue you are facing?

For more information on Cost center distribution you can refer the below link:

http://help.sap.com/saphelp_47x200/helpdata/en/08/514e2e43b511d182b30000e829fbfe/content.htm

If your doubt is how to use the sender & receiver cost centers in distribution.

e.g. create cost center group (CSG01) and assign the below cost centers:

2101000000 to 2101010100

2101010102

2101010104 to 2101000329

Create one more cost center group (CSG02) and assign the below cost centers:

2101010101

2101020103

Maintain the above cost center groups in Distribution segment.

Also maintain receiver tracing factor as Fixed percentages.

Let me know if you need further details.

BR

ADI