Dear Guru,
How to use discontinued and follow up material with effective date. I am using MTS Scenario.
Please help.
Regards,
Sanjay Sahoo
Hi,
In MRP-4 view, you need to select the Discontinuation indicator, effective out date and the follow up material.
Discontinuation indicator: 1, simple discontinuation, 2. Parallel discontinuation. this we need to define there. Simple means immediately it will set the discontinuation indicator. Parallel means, once the current stock consumes then this will come in to effect.
Effective date means we need to define the date from when this will be discontinued.
Follow up material means we need to define the follow up material in this field.
Regards,
V. Suresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks a lot.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanjay,
refer to the below link, it should answer your query:
In addition to the above details:
In material master for the material which is being discontinued, in MRP-4 view you need to maintain discontinuation indicator, effective-out date & Follow-up material.
If you need any additional info, revert.
If helpful award points
Regards,
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
8 | |
6 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.