Hi Friends,

i want to know how to maintain Discontinued parts and how to do Production for these discontinued materials. Discontinued materials means, materials which are already half completed and the client wants now to be taken into SAP system. please help me.

Thanks & Regards,

Santosh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Discontinued materials in SAP means:

If you want to use some of the components in place of the original components & these orriginal components , you are

no more using.

In the material master if you enter dicontinued material

system will propmt you to give effective out date.

That means from which date you are going to use the substitute material.

These fileds are in Materia master MRP 4 view

Hope it is clear.

Regards

YMREDDY

santosh_kanta3
Participant
0 Kudos

Hi Reddy,

Thanks for ur reply.

Actually the problem is there are few items lying in the stock. for e.g a Material XYZ consists of 10 operations. the discontinued materials which are lying in the stock are few materials which have completed first 2 operations, few which have completed first 4 operations and few materials which have completed first 6 operations. tell me how to take in the production? please help me out.

Thanks & regards,

Santosh

Former Member
0 Kudos

Dear,

create manual production order and issue these materials to production order...delete the operations which are not required in production order routing screen. Confirm the production order operation and do GR and get the product qty into store

pl come back if required.

santosh_kanta3
Participant
0 Kudos

Hi Rajesh,

thanks for ur reply. how to take these materials into stock. how the system will consider these materials while doing Availability check. actually we are in testing stage. now the client has given this issue. we have already created Halb & Fert materials. these discontinued materials come under these materials.

Thanks & regards,

Santosh

Former Member
0 Kudos

HI,

Already produced materials go to intial stock posting route.

For Under production materials,

As Rajesha suggested, create production orders and cancel or confirm the operations completed.

then proceed as required.

santosh_kanta3
Participant
0 Kudos

Hi Ratan,

thanks for ur reply. how to do that initial stock posting?

please explain me.

Thanks & Regards,

Santosh

Former Member
0 Kudos

Dear,

Using MB1C - Movement type 561...take the material into inventory...

santosh_kanta3
Participant
0 Kudos

Hi Rajesh,

Thanks for ur reply. but tell me what should i consider these type of materials? raw material or semi - finish? the secnario is as follows:

Raw Material consumption

Op/ Activity Description Qty

10 Profile Cutting 10 nos.

20 Rough M/cing VTL 07 Nos

30 .................... 06 nos

40 ..................... 00 nos

50 .................... 10 nos

60 .................... 09 nos

70 ................... 00 nos

... .................... 11 nos

... ................ 00 nos

... ...................... 12 nos

.... .................... 06 nos

120 ...................... 09 nos

All these operations comes under a single material code Semi Finish. so the problem is where (S.Loc) to consider while taking into opening stock? please give the solution.

Thanks & Regards,

Santosh

Answers (1)

Answers (1)

Former Member
0 Kudos

is it solved?

santosh_kanta3
Participant
0 Kudos

Hi Rajesh,

Thanks for ur reply. the problem is not solved. so please tell me how to do.

Thanks & Regards,

Santosh