Difference in Requirement Quantity and Commited Quantity In Process Order

Former Member
0 Kudos
782

Dear All,

I have a situation here ,

In a process order (Cor3)

there are 4 components of same materials but ofcourse of different batches.

But to the surprise of one Item no.0010 in the material component tab there is a differnece between Requirement quantity and Commited(confirmed) quantity,

Even though , i can see full availability of Material Stock in MMBE.

Requesting suggestion for a probable reason.

View Entire Topic
Former Member
0 Kudos

Hi Chandan,

It is probable that the material/stock is already committed to other requirements.

Please check the availability overview for the referred component through CO09.

If you still find the item available, please try running availability check the the order/component (COR2 or COHVPI).

Regards,

Senthil