on 2024 Jun 05 6:20 AM
Hi!
We already use the material DIEN (ZDIEN for purchasing) to process services.
We are now planning to start using PM orders.
What are the risks if we continue to use DIEN instead of the service masters?
What is the best practice?
Thanks.
Request clarification before answering.
Hi,
The DIEN material type in the SD module, In Plant Maintenance if you're using DIEN material type the process will be similar to PM02, where there is no service entry sheet, and the goods receipt (GR) is processed directly.
You can also refer to this link DIEN material type in PM order