Hi PM Experts,

How can i make a deviation report for delayed work or reworks?

What are the Tcodes to be used?

Is there a required configurations for that?

Thank you

Accepted Solutions (1)

Accepted Solutions (1)

rakesh_mane
Active Contributor
0 Kudos

Dear,

Use TC Iw41 and enetr reason for delay and enete the Confirmation text.and enetr the remaining working hours and actual working hours.Dont click the Fianl confirmation check box coz ur work is delayed and also dont click the check box of No remaining working den save it. den use TC IW47 click the In process check box and execute itand u will get the deviation report and its causes which is u filled in it

Regards

Rakesh

Former Member
0 Kudos

i was able to try it. it worked well.

thank you so much rakesh..