Dependent requirements not triggered for a component (Incomplete explosion of BOM components)

Former Member
0 Kudos

Hi PP experts

Dependent requirements not triggered for a component (Incomplete explosion of BOM components)

Planned orders from APO for FG product, a component is missing in planned order (BOM not exploded completely in ECC). Whereas when we created a planned order manually in ECC, complete list components are existing in Planned order. For the SNP planned Orders only one component (out of many ROH components) is missing in Planned order there by no dependent requirements triggered  for that component

Checked BOM validity dates for missing component, lot size of component in material master & Production Version for FG, everything seems to be in place.

Let me know the probable root cause & solution for the said problem

Thanks in advance

Manju

Accepted Solutions (0)

Answers (2)

Answers (2)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Manju

This issue is described on the following note:

717826 - APO->R/3 components are missing in R/3

The following solution is provided on the note:


Check your integration models and regularly execute the RAPOKZFX program.
You should also use all APO-relevant components from your BOM in your SNP-PPM or PDS as well, as otherwise they will not be copied to the R/3 planned order. The R/3 system assumes that APO-relevant components that are not sent from APO should not be copied to the R/3 planned order.

BR

Caetano

Former Member
0 Kudos

HI Caetano

We were regularly executing RAPOKZFX program & we used all APO relevant components in SNP PDS

Still the issue is exist, any solution/inputs on the same will be appreciable

Thanks

Manju

former_member222080
Participant
0 Kudos

Hello Manju

Please check the MRP type for the component

suresh

Former Member
0 Kudos

HI Suresh

MRP Type for the component is PD