I have a FERT with one component HALB.

I enter PIR's for HALB's to bring them in ahead of time as they have 3 month lead time (with no project#).

FERT demand gets created when a reservation is created against a created project.

Now when I run MRP, I want the PIR for the HALB to get reduced by the dependent requirements amount so we don't double order.

Bear in mind the FERT has a project# and the HALB does not. Also, sales orders use a dummy part# just to charge customer, so no sales order involvement with these parts.

Any ideas?

 

View Entire Topic
matjazmoser
Active Participant

Greetings,

you need to define:

  • proper strategy group
  • consumption mode
  • consumption period (forward and backward)
  • mixed MRP

matjazmoser_1-1719822013808.png

There is a pretty nice blog available:

https://community.sap.com/t5/enterprise-resource-planning-blogs-by-members/planning-strategy-70-plan...