Hello,

I have the PIRs which are to appear in three rows - PIR, Additional PIR & Buffer PIR. The break-up is a requirement. The system should cumulate the PIRs while considering the demand. How this can be achieved in SAP system?

Regards.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

When creating requirements thru MD61 select the requirement plan radio button & create three different plan as

PIR, additional PIR , Buffer PIR.

Try this & revert.

Regards

Mithun

Former Member
0 Kudos

Thank you Mithun. It is a good solution.