on 2014 May 12 8:06 PM
Hi everyone.
We know, in the division of delivery schedule in ME38 transaction, we program the delivery date, on standard we can't do the MIGO in an period before the date programed in ME38.
But my customer need take it off this standard validation.
They need do the MIGO even if the delivery date has not been reached.
We have some way to do that on customizing?
Thanks for now.
OSS note 741385 - Goods receipts up to current date for scheduling agreements explains a solution with user exit.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.