on 2012 Oct 03 10:31 PM
Hi all,
we are using EDI to send PO or delivery schedule (LP) to vendor.
condition record and partner profile is maintained. Create message for delivery schedule is working fine, but when i change the deliveyr schedule, output message is triggered but it failed.
the error is. please help me on this. For po change it is working fine only issue with delivery schedule.
Message no. ME760
Check the IMG under Materials Mgmt > Purchsaing > messages > fields relevant to printout of changes.
Check the entry for EKET-EINDT, indicator towards the end for '
Specifies whether this field is relevant to change notices (printouts of changes) involving scheduling agreements.