on 2023 Mar 03 9:22 AM
Dear SAP experts,
When using delivery from project (CNS0), delivery type LP, the standard Movement type for GI is 281(Q).
For a customer this needs to be changed to 601(Q) for the COGS split.
Valuated project stock is in use.
Is there a way in customizing to change the GI movement type only for delivery from project?
Thanks for your help.
Since the Delivery is being created in reference to the Project and not a Sales Order you need to use the 281 Movement Type so the costs properly flow to the project. See if you can apply your COGS split settings to this movement type.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.