on 2023 Mar 03 9:22 AM
Dear SAP experts,
When using delivery from project (CNS0), delivery type LP, the standard Movement type for GI is 281(Q).
For a customer this needs to be changed to 601(Q) for the COGS split.
Valuated project stock is in use.
Is there a way in customizing to change the GI movement type only for delivery from project?
Thanks for your help.
Hi,
Check t-code OPT1 and try changing the movement type to the one you want the system to derive when using CNS0.
Let us know if that helps.
Thanks,
Gokul