Delivery Date triggering lesser than the PO Document Date

Former Member
0 Kudos

Hi Experts,

Please help in certain batch jobs Cross Company PO, The delivery date is appearing lesser than the PO Document date/Created on date.

As checked in Material master the GR processing Time is available. For this Purchase Order, PR has been triggered thru MD04 and converted thru PO.

And checked for some other PO which created thru batch jobs, Delivery date is calculating correctly and material master setup in MRP1, 2  maintained same as above for above PO material. Please advice.

Regards

Karthik Angappan.

Accepted Solutions (0)

Answers (1)

Answers (1)

JL23
Active Contributor
0 Kudos

MD04 does not trigger anything automatically, it displays existing PR and you can convert them manually into a PO from here.

So you should check if these were old PRs which got created a couple days earlier and have not been processed.

Former Member
0 Kudos

Hi Jurgen,

Please I have checked for 1 PR document, Whereas the Requisition Date, delivery date, release date is appearing as 01.09.2016

Our worry is why delivery date is not triggering the future date from the date of creation, Please will there be any issues in route is that inter related to delivery dates trigger.

Regards,

Karthik Angappan.

JL23
Active Contributor
0 Kudos

you want to say you have 2 purchase requisitions for the same material and requisition 1 which got converted into a PO by a batch job has proper delivery dates, while requisition 2 which is manually converted does not have proper delivery dates?

Former Member
0 Kudos

Hi Jurgen,

no its 1 PR document for 1 material.

While converting into PO by Batch Jobs, We have several material got created (All different material and PR docs). Only date is same for PR creation date, Delivery Date, Release date as 01.09.2016.

Whereas delivery date should be triggered in future, Please why its not happening.

Regards,

Karthik Angappan.

JL23
Active Contributor
0 Kudos

does the  PO creation change the delivery date?

IF not, then you can just ignore the way how a PO is created and can focus on the creation of the PR only.

Former Member
0 Kudos

Hi Jurgen,

Please PO creation doesn't change delivery date. Its appearing from PR only.

Is there is a way to find why delivery date is not calculated.

Regards,

Karthik Angappan.

JL23
Active Contributor
0 Kudos

sure, by checking/correcting the master data, and doing a retest. 

You initially said "GR processing Time is available" , have you cross checked the documentation if the GR processing time has at all some influence on the time that your vendor needs to get the goods from his plants to yours?

BijayKumarBarik
Active Contributor
0 Kudos

Hi,

What is message status of following message numbers

ME-589

06-245

Are you use concept of Date of Availability and Self Life Expiration Date for  that material.

Regards,

Biju K