cancel
Showing results for 
Search instead for 
Did you mean: 

Delivery date in Purchase order

0 Kudos
839

Hi,

How is delivery date in PO calculated?

I know that field "Planned delivery days" in the Purchase info record contributes in determining the delivery date. Which other fields in the master data contributes to the delivery dates?

Thanks in advance!!!

Regards.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member337117
Contributor
0 Kudos

Suraj,

Delivery date in PO is calculated either from PR (if PO is created wrt PR) else, material master (Planned delivery time) or purchasing master data record such as contract or info record. If none of the above parameters are maintained, then delivery date will considered as 0 and will display PO creation date as delivery date.

Regards,

Vignesh Bhatt