Hi All,

We have created a STO with the delivery date as 02.17.2011...

When we execute the program SAPMV50S....it creates delivery for the above PO even though its delivery date is in Feb.

We executed SAPMV50S with date range as sy-datum + 2 days.

On analysis we found that the STO was having committed date as 01.18.2011.....

It is clear that the program considers the committed date to create deliveries....question here is ..can we change it via some config....or is some standard program available wherein it considers the delivery date and not committed date?

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member212005
Active Contributor
0 Kudos

Solved!!

Former Member
0 Kudos

can you tell me how did u do it?