I have Created PO and Released for Quantity 400. Now 200 was delivered. Now we decided to stop the further deliveries. what to do??? Delivery completed Indicator in Disable mode? Please suggest me.

View Entire Topic

If the delivery completion indicator is set for partial delivered PO, System doesn't stop you from taking GR for remaining qty.

Either you should use latest GR possible date (along with error msg set). Or

Change the PO qty to delivered qty. ME22N

0 Kudos

Hii...

Thanks for the response...Should I revoke the PO to do changes in PO quantity??? Is there any other way??

If I revoke the PO to adjust the Quantity... what is the effect on Invoice?