on 2020 Sep 15 11:58 AM
I have Created PO and Released for Quantity 400. Now 200 was delivered. Now we decided to stop the further deliveries. what to do??? Delivery completed Indicator in Disable mode? Please suggest me.
Request clarification before answering.
If the delivery completion indicator is set for partial delivered PO, System doesn't stop you from taking GR for remaining qty.
Either you should use latest GR possible date (along with error msg set). Or
Change the PO qty to delivered qty. ME22N
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.