defining a Cost center & Activity types

Former Member
0 Kudos

hi thr ,

can any body plz tell me the procedure in details for

defining a Cost center & Activity types for the SVK parameter in DETAILS

which is assigned in the work center --> costing screen .

Plz send me the detailed procedure step by step , if possible with Screen shot & TCODES

Regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Ajay,

1) Create cost element - KA01

2) Create activity type - KL01 and assign cost element

3) Create cost center - KS01

4) Assign price for cost cnter/ activity - KP26

5) Assign activity to std value - CR02

regards

Ram

Answers (1)

Answers (1)

Former Member
0 Kudos

IN THE NAVIGATION PATH

FOR IMG --- CONTROLLING -


COST CENTER ACCOUNTING -- MASTER DATA - COST CENTER AND BELOW TO THAT- ACITIVITY TYPES

HERE YOU CAN DEFINE THE COST ELEMENTS FOR THE ACITIVITIES

(iI)CREATE COST CENTER

(iii) CREATE ACTIVITY TYPE