Define PRT Status

former_member217512
Participant
0 Kudos

Hi,

In IMG->PRT- General  Data- Define PRT status.

We will be defining different PRT Statuses (Definition of - Allocation for Planning and Allocation for Production).

Could some one help me- How to assign these Statuses to Equipment PRT in IE25?

How this statuses are useful in business?

Thank you

Renjith.

Accepted Solutions (1)

Accepted Solutions (1)

S0022314014
Active Contributor
0 Kudos

Renjith

These status are assigned to PRT miscellaneous (sometimes called PRT Other or PRT master Data as well) which are created with transaction CF01.

The status can block the usage of a PRT in any Task List or Order. If there is an engineering department which designs some PRTs as prototypes with different engineering status which allows/disallows usage of those PRTs with certain restrictions. In different buseinss cases of Production (PP), there are usages of these prototypes... Currently in standard PM, there are not any further usage of those statuses.

You cannot assign those status to Equipment PRT or any other type of PRT.

Regards

Savas

former_member217512
Participant
0 Kudos

Hi Savas,

Thank you...

Answers (0)