on 2012 Feb 16 3:40 PM
Hi SAP Experts,
Greetings to all. I wish to ask one question:
I need to do the Batch Management but just wanted to know how to handle following scenario:
"Batch consist of x number of materials and one material in the batch is defective".
I dont want to Block the whole batch for only one material.
Please suggest how to handle this scenario.
Best Regards,
UK.
create another batch in MSC1N, then move this 1 defective part with MIGO and movement 311 from the old to the new batch