Hi,

I am trying to understand where SAP is holding information on the date of change of status of Proces (or Production) order to TECO or DLV. I think that this information must be held somewhere as based this date is being used to calculate variance for production orders in KKS2 or KKS1 transaction.

Thank you,

Karol

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Karol,

Make sure you have activated the change documents in OPL8 / COR4 tab Implementation.

Co03

-> Button with the blue I to insert the status overview

-> Menu Extras / Change documents

BR Sabine

Former Member
0 Kudos

Dear Sabine,

Thank you for your explanation.

Best regards,

Karol

Former Member
0 Kudos

Dear Sabine,

I checked a table where these dates are kept. It is JCDS table, but statuses shown in it are different, like I0001 or I0420. Do you know if there is a relation between these statuses codes and TECO or DLV status in Production orders.

Is there another table that defines mapping of statuses used in JCDS table with the statuses we know from Production orders.

Thank you,

Karol

Former Member
0 Kudos

Dear Karol,

yes their is one. Goto BS23 here you see which internal number is assigned to which status. For example created (CRTD) is I0001 or delivered (DLV) is I0012.

Additional table is JEST

BR Sabine