on 2011 Jan 18 9:26 AM
Dear All,
We have come across one issue at client side, for which we need ur help.
client made sum payment to employee in april'10 for december month 2009, but thats not getting added in /125 for this year
in CWTR its showing as for period 092009.
what could be the possible solution for this error
Plz help.
Rgds,
Zara
Closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
the wage type is irregular income so it will cumulated only for the month which was been paid kindly check
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This is not an error it is a feature.
Since the payment is dated December 2009, system will treat it as a payment FOR December 2009 IN April 2010. So it will show up in the CWTR against for-period December 2009.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
8 | |
6 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.