hi professionals,

plz go through the scenario,

we are having two plants PLANT1 & PLANT2

PLANT1 is planning plant.

sales and purchasing are allowed only for PLANT1 in PLANT2 only some production takes place.

we have to maintain both of em as plants, not as a plant and work center.

finished product A is made of B and C( raw material), with co-products D and E.

B is semifinished material produced in PLANT1 with co-product D and raw material Z.

then B gets transferred to PLANT2, where finished product A is produced.

Please reply to us how we can do the planning for this particular scenario.

thanks

regards.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi ,

You can show this material as a stock transfer through MM (301 movement type) module and

If you go to Z development you will have to write programme for the same When 101 will happen same time in background 301 also happens.

Former Member
0 Kudos

Hi

This can be done by using special procurement key as produced in other plant (80) or 70 for material B in plant 2. So that it will transfer all the dependent req for B from plant 2 to plant 1. check customizing for spl proc type where u can specify the alternate plant.

Regards